construction project site with hardhats

SDG&E Power Project

Construction Support and Logistics for:

SDG&E's $1.9 Billion Electrification Project

Construction Support and Logistics for:

SDG&E's $1.9 Billion Electrification Project


Challenge: 

Constructing 117-miles of 230/500 kilovolt power line


SDG&E required comprehensive construction support logistics for one of California's most complex high-voltage transmission infrastructure projects, a 117-mile, 230/500 kilovolt power line spanning five geographically distinct links across remote desert, protected state parkland, and densely populated urban corridors. The scale, terrain diversity, and multi-jurisdictional footprint of the project demanded a coordinated materials management and site readiness strategy capable of sustaining continuous construction progress across more than 150 miles of active right-of-way, including segments accessible only by air.


Approach: 

Regional hubs and helicopter flights


The team was engaged to establish and operate a network of strategically positioned "laydown" yards across all five-project links totaling over 150 miles. Each yard was sited and configured to serve as a regional hub for receiving, inventorying, staging, and dispatching materials and supplies to active construction crews, including coordination of the 30,000 helicopter flight hours required to access remote tower locations. Responsibilities encompassed end-to-end project logistics from sourcing point to field delivery, real-time inventory management aligned to construction scheduling, and enforcement of site safety and security protocols across all onsite yards.


Outcome: 

On-schedule delivery of 1,000 megawatts


The laydown yard network and integrated logistics program enabled uninterrupted material flow across a geographically demanding, multi-link transmission corridor, supporting on-schedule energization of the line in June 2012. By maintaining supply chain continuity across varied terrain and regulatory environments, the team helped protect the construction schedule on a $1.9 billion electrification project delivering 1,000 megawatts of renewable energy capacity to the San Diego region.